Old Main
- Contractor:
- Built: 1898
- Architect:
- Project Cost: $0,000,000
- New Space: 76,626 sq ft
- Completion Date: 0/0/0000
Old Main was the first building of the UMD campus. It was listed in the National Register of Historic Places, and was originally the main building of the Duluth Normal School, which was a teachers college. An arson fire that occured Tuesday February 23, 1993 destroyed the building. Demolition began on Monday March 1, 1993 and ended May 20, 1993. The site was later donated to the City of Duluth.
Washburn Hall
- Contractor:
Construction Start Date:
- Architect:
- Project Cost: $35,000
- New Space:
- Completion Date: September 1906
Washburn Hall was named after Duluth attorney J.L. Washburn, for his donation of $6,000 to its construction. It served as the first ladies campus dormitory.
Research Laboratory
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
Originally the Laboratory School for the DSTC students, the Research Laboratory was previously the first School of Medicine and first Natural Resources Institute.
Chemistry
Phase I:
- Construction Start Date: 10/19/1948
- General Contractor: A. Hedenberg Construction Company
- Mechanical Construction: Martin Wold
- Outside Utilities: Martin Wold
- Electrical Construction: Commercial Electric
- Project Cost: $600,000
Phases II and III:
- General Construction: Kileen & Wille
- Mechanical Construction: Martin Wold
- Electrical Installation: Commercial Electric
- Architect: A. Reinhold Melander
- Project Cost: $261,611
- Completion Date: Fall 1951
The Chemistry Building was originally named The Science Building until 1973.
Sports and Health Center
- General Contractor: A. Hedenberg Construction Company
- Mechanical Construction: Carlson-Miller Company
- Electrical Installation: Universal Electric Company
- Construction Start Date: July 1951
- Architect: A. Reinhold Melander
- Project Cost: $1,602,000
- Completion Date: 9/14/1953
The Sports and Health Center was originally named Health and Physical Education Building. The ROTC building was moved to the Darland Building from the original site east of the Sports & Health Center to accomodate the addition in 2005.
Sports and Health Center Addition
- Architect: RDG Sports & Stanius Johnson Architects
- Estimated Project Cost: $13,000,000
- New Space: 46,000 gross square feet
- Construction Start Date: June 2005
- Completion Date: November 2006
ROTC
- General Contractor: Allied Steel Company
- Heating and Plumbing: Contracted locally
- Electrical Installation: Done by the university electricians.
- Construction Start Date:
- Architect: Done in-house by Mr. Harry Wilson and Mr. Bridges; who were engineers for the Minneapolis and UMD campuses.
- Project Cost: $41,954
- Completion Date: late 1953
The ROTC Building was removed in 2006 and the ROTC offices were relocated in the Darland Administration Building.
Kirby Plaza
Phase I
- General Contractor: Fowler- Veranth Const. Co.
- Plumbing and Heating: Carlson-Miller Company
- Ventilation: Zimm Sheet Metal Company
- Electrical Construction: Universal Electric Company
- Passenger Elevator: Westinghouse Elevator Company
- Freight Elevator: Johnson Elevator Company
- Construction Start Date: 4/20/1954
- Architect: A. Reinhold Melander
- Project Cost: $760,000
- Completion Date: September 1955
Phase II
- General Contractor: A. Hedenberg and Co.
- Mechanical Construction: A. G. O'Brien Plumbing and Heating
- Electrical Installation: Universal Electric
- Construction Start Date: 7/23/1964
- Architect: Melander and Associates
- Project Cost: $958,000
- Completion Date: 7/23/1964
Phase III
- General Construction: A. Hedenberg Company
- Mechanical Construction: A. G. O'Brien
- Electrical Installation: Nylund Electric Company
- Elevator Installation: R. & O. Elevator Company
- Construction Start Date: April 1966
- Architect: Melander and Associates
- Completion Date: Spring 1967
Kirby Plaza was originally the old Library.
Kirby Plaza
- New Space: 121,000 gross sqft
- Project Cost: $20,000,000
- Architech: Design Architect - Krech Ojard and Associates
- Contractor: Johnson Wilson Constructors & UMD Facilities Management
Kirby Student Center
- General Contractor: J. D. Harrold
- Mechanical Construction: Carlson-Miller Plumbing and Heating
- Electrical Installation: Commercial Electric
- Elevator Installation: Otis Elevator Co.
- Construction Start Date: 9/29/1954
- Architect: A. Reinhold Melander
- Project Cost: $1,300,000
- Completion Date: 1956
Kirby Student Center was named for Stephen R. Kirby, who donated $400,000 towards the building of a student center.
Vermilion Hall
- General Contractor: Fowler-Veranth
- Mechanical Construction: Carlson Duluth
- Electrical Installation: Commercial Electric
- Elevator Installation: Otis Elevator Co.
- Construction Start Date: 9/29/1954
- Architect: A. Reinhold Melander
- Project Cost: $303,706
- Completion Date: 1956
Vermilion Hall was named for the Northern Minnesota Lake
Heller Hall
Phase I
- General Contractor: J. D. Harrold
- Mechanical Construction: Carlson-Miller
- Electrical Installation: Universal Electric
- Construction Start Date: May 1956
- Architect: A. Reinhold Melander
- Project Cost: $575,000
Phase II
- General Contractor: Klippen & Holm
- Mechanical Construction: Axel Newman Heating and Plumbing
- Electrical Installation: Arrowhead Electric
- Construction Start Date: July 1957
- Architect: A. Reinhold Melander
- Project Cost: $105,000
- Completion Date: Spring 1965
Heller Hall was originally the Science Building addition, then Mathematics-Geology Building before being named after Chancellor Emeritus Robert L. Heller on September 30, 1988.
Humanities
- General Contractor: A. Hedenberg
- Mechanical Construction: Modern Contractors
- Electrical Installation: Arrowhead Electric
- Construction Start Date: 5/22/1956
- Architect: Jyring and Whiteman
- Project Cost: $800,000
- Completion Date: 3/15/1958
Humanities Fourth Floor Addition
- Construction Start Date: May 1963
- Architects: Jyring and Whiteman
- General Contractor: Fraser Wipson Co.
- Mechanical Construction: O’Brien Plumbing & Heating Co.
- Electrical Installation: Arrowhead Electric Company
- Total Project Cost: $465,200
- Completion Date: Summer 1964
Cina Hall
- General Contractor: J. D. Harrold
- Mechanical Construction: Martin Wold
- Electrical Installation: Universal Electric
- Elevator Installation: Otis Elevator Co.
- Construction Start Date: 4/25/1958
- Architect: Melander-Fugelso
- Project Cost: $800,000
- Completion Date: 6/25/1959
Cina Hall was originally the Social Science Building. The Building was renamed in 1985 in honor of UMD Regent Fred A. Cina .
Heating Plant
- General Contractor: J. D. Harrold
- Boilers and Mechanical work: Carlson-Duluth
- Construction Start Date: July 1958
- Architect:
Jyring and Whiteman (building)
G. M. Orr Engineering (boilers, mechanical equipment, and structural mountings for equipment)
- Project Cost: $319,634
- Completion Date: August 27, 1959
First Heating Plant Addition
- Construction Start Date: 1968
- Architect: (Building Modifications/Additions) Aguar, Jyring, Whiteman and Moser; (Mechanical Work and Boiler) Orr-Schelen-Mayerson and Associates
- General Contractor: Wipson, Inc.
- Mechanical Construction: A. W. Kuettel & Sons
- Electrical Installation: Arrowhead Electric
- Total Project Cost: $441,074
- Completion Date: Spring 1971
Coal Gasifier Addition to Heating Plant
- Construction Start Date: Summer 1977
- Architect: Architectural Resources, Inc., Architects
- General Contractor: A. Hedenberg Company
- Mechanical Construction: Healy, Inc.
- Electrical Installation: Electric Construction Company
- Coal and Ash Handling Equipment: Reuben L. Johnson
- Total Project Cost: $3,337,269
- Completion Date: September 1978
Burntside Hall
- General Contractor: A. Hedenberg
- Mechanical Construction: C. Walter Carlson
- Electrical Installation: Commercial Electric
- Construction Start Date: May 1958
- Architect: A. Reinhold Melander
- Project Cost: $525,323
- Completion Date: Summer 1959
Burntside Hall was named for the Northern Minnesota Lake.
Bohannon Hall
- General Contractor: A. Hedenberg
- Mechanical Construction: Sher's Contractors
- Electrical Installation: Collins Electric
- Construction Start Date: 9/14/1960
- Architect: Melander, Fugelso & Associates
- Project Cost: $850,000
- Completion Date: 1961
Bohannon Hall was originally the Education Building. It was renamed May 22, 1974 for Dr. Eugene W. Bohannon, who served as the Duluth Normal School's first president from 1901-1938.
Lecture Hall Addition Boh.90
- Construction Start Date: Spring 1964
- Architect: Melander, Fugelso and Associates
- General Contractor: J. D. Harrold and Company
- Mechanical Construction: A. G. O’Brien Plumbing and Heating Company
- Electrical Installation: Universal Electric Company
- Total Project Cost: $200,000
- Completion Date: 1965
Completion of Bohannon
- Construction Start Date: February 1966
- Architect: Melander, Fugelso and Associates
- General Contractor: Amendola Construction Company
- Electrical Installation: Arrowhead Electric, Inc.
- Elevator Installation: Otis Elevator Company
- Total Project Cost: $77,500
- Completion Date: Summer 1966
Concourse A
- General Contractor: J. D. Harrold
- Mechanical Construction: Martin Wold
- Electrical Installation: Commercial Electric
- Construction Start Date: November 1960
- Architect: Melander, Fugelso and Associates
- Project Cost: $247,686
- Completion Date: 12/5/1961
Information about building of interest?
Voss Kovach Hall
- General Contractor: J. D. Harrold
- Mechanical Construction: C. W. Carlson
- Electrical Installation: Arrowhead Electric
- Elevator Installation: Johnson Elevator
- Construction Start Date: November 1960
- Architect: Jyring and Whiteman, Inc.
- Project Cost: $950,000
- Completion Date: February 1962
Originally called the Industrial Education building, Voss Kovach Hall was named for Gordon O. Voss and Frank J. Kovach, an industrial education professor and Bulldogs coach.
Montague Hall
- General Contractor: J. D. Harrold
- Mechanical Construction: O'Brien Plumbing and Heating
- Electrical Installation: Arrowhead Electric
- Elevator Installation: Otis Elevator Co.
- Construction Start Date: 5/6/1963
- Architect: Melander and Fugelso
- Project Cost: $931,894
- Completion Date: Fall 1964
Montague Hall was originally called the Home Economics Building and was renamed October 4, 1982 in honor of William K. Montague. William K. Montague served as a University of Minnesota Regent from 1963-1969.
Griggs Hall
Phase I
- General Contractor: J. D. Harrold
- Mechanical Construction: Martin Wold
- Electrical Installation: Commercial Electric
- Construction Start Date: 6/30/1964
- Architect: Jyring and Whiteman, Architects
- Project Cost: $929,965
- Completion Date: August 1965
Phase II
- General Construction: Johnson- Gillanders
- Mechanical Construction: A. G. O'Brien Plumbing and Heating
- Electrical Installation: Arrowhead Electric
- Construction Start Date: June 1966
- Architect: Jyring and Whiteman, Architects
- Project Cost: $1,020,000
- Completion Date: Fall 1967
Griggs Hall was named for businessman Richard L. Griggs. Griggs was also University Regent from 1939-1963, as well as a patron and financial supporter of UMD.
Griggs Field
- General Contractor: Paulson Brothers
- Electric Scoreboard: Naden Industries
- Lighting: Commercial Electric Co.
- Concrete Bases for Lighting: Paulson Prothers
- Bleachers: Hauenstein-Burmeister Co.
- Construction Start Date: August 1966
- Architect: Aguar, Jyring Whiteman and Moser
- Project Cost: $198,568
- Completion Date: 10/29/1966
Griggs Stadium was named for Richard L. Griggs.
Outside sheathing and press box addition
- General construction: Paulson Brothers
- Electrical Installation: Commercial Electric Company
- Construction Start Date: June 1968
- Architect: Melander, Fugelso and Associates
- Completion Date: November 20, 1968
Marshall W. Alworth Planetarium
- General Contractor: Wille Construction
- Mechanical Construction: Metalcraft
- Electrical Installation: Arrowhead Electric
- Planetarium Dome and Equipment: Spitz Laboratories
- Construction Start Date: 10/13/1965
- Architect: Melander, Fugelso, & Associates
- Project Cost: $194,440
- Completion Date: Spring 1967
Formerly the Darling Observatory, the Planetarium was renamed for Marshall W. Alworth. Alworth, a prominent Duluth businessman, funded the entire building's construction.
Concourse B
- General Contractor: Pavola Construction
- Mechanical Construction: Al Carlson and Sons
- Electrical Installation: Arrowhead Electric
- Construction Start Date: May 1965
- Architect: Melander, Fugelso and Associates
- Project Cost: $95,000
- Completion Date: Summer 1966
information about building of interest?
Life Science
- General Contractor: A. Hedenberg
- Mechanical Construction: A. G. O'Brien Plumbing and Heating
- Electrical Installation: Commercial Electric
- Elevator Installation: R. and O. Elevator
- Construction Start Date: 9/29/1966
- Architect: Melander, Fugelso and Associates
- Project Cost: $1,440,543
- Completion Date: 1968
Originally housing science labratories and offices, an addition in 1968 added space for 2 lecture halls adjacent to the building. It wasn't until 1983 that the greenhouse was added.
With the renovation in 2007 this LEED certified building now houses the College of Pharmacy and Department of Biology.
Science Lecture Halls Addition
- Construction Start Date: November 1968
- Architect: Melander, Fugelso and Associates
- General Contractors: Paulson Brothers
- Mechanical Construction: A. W. Kuettle and Sons, Inc.
- Electrical Installation: Commercial Electric Company
- Total Project Cost: $360,000
- Completion Date: 1970
Greenhouse Addition to Life-Science
- Construction Start Date: November 28, 1983
- Architect: Edward Schafer Associates, Inc.
- General Contractors: Erling R. Housen Company
- Mechanical Construction: Stout Mechanical
- Electrical Installation: Nylund Electric Company
- Total Project Cost: $349,000
- Completion Date: late October 1984
Life Science Renovation
- Renovated Space: 72,588 gross square feet
- Project Cost: $15,200,000
- Construction Start Date: January 2006
- Completion Date: July 2007
- Architect: LHB Engineers & Architects Health, Education & Research Association - Lab Consultants
A. B. Anderson Hall
- General Contractor: United General Constructors
- Mechanical Construction: A. G. O'Brien Plumbing and Heating
- Electrical Installation: Electric Construction
- Construction Start Date: 10/22/1968
- Architect: Morgenstern, Stanius, Thorson
- Project Cost: $990,000
- Completion Date: Fall 1970
A.B. Anderson Hall was originally called the Classroom-Office Building and was renamed on September 8, 1973 in honor of Adolph Benoni Anderson. A.B. Anderson had been working towards establishing a University of Minnesota campus in Duluth since the 1930’s.
Darland Administration Building
- General Contractor: Twin City Construction
- Mechanical Construction: Healy Mechanical
- Electrical Installation: Electric Service
- Elevator Installation: R & O Elevator
- Construction Start Date: 12/23/1969
- Architect: Melander, Fugelso and Associates
- Project Cost: $2,399,785
- Completion Date: Summer 1971
Darland Administration Building was originally named Administration Building before being named for Dr. Raymond W. Darland on June 25, 1982. Darland taught biology at UMD before becoming dean until his retirement in 1981.
Lake Superior Hall
- General Contractor: United General Contractors
- Mechanical Construction: Sher's Contractors
- Electrical Installation: Commercial Electric
- Elevator Installation: Johnson Elevator
- Construction Start Date: 6/24/1969
- Architect: Aguar, Jyring Whiteman & Moser
- Project Cost: $2,550,000
- Completion Date: Summer 1971
Lake Superior Hall was named for the Great Lake.
Stadium Apartments
- Contractor:
Kraus - Anderson of Minneapolis, Inc.
- Construction Start Date: June 1972
- Architect: Architectural Alliance of Minneapolis & Augar, Jring, Whiteman & Moser, of Duluth
- Project Cost: $2,826,000
- Completion Date: December 1973
Originally known as Single Student Housing the building was named Stadium Apartments in June 1973.
Lund
- General Contractor: Reuben Johnson & Sons
- Mechanical Construction: Martin Wold
- Electrical Installation:
- Construction Start Date: 3/28/1972
- Architect: Aguar, Jyring Whiteman and Moser
- Project Cost:$460,000
- Completion Date: Winter 1972-1973
The Lund Building was originally named Plant Service Center before being named for Roy V. Lund.
Marshall Performing Arts Center
- General Contractor: Wille Construction
- Mechanical Construction: A. G. O'Brien
- Electrical Installation: Commonwealth Electric
- Stage Rigging Construction: Northwest Studios
- Elevator Installation: Johnson Elevator and Stage Lifts
- Auditorium Seating: St. Paul Book & Stationery
- Construction Start Date: September 1971
- Architect: Melander, Fugelso, Porter and Simich
- Project Cost: $2,760,251
- Completion Date: Winter 1973-74
The Marshall Performing Arts Center was named for its generous benefactors, sisters Caroline Marshall, Julia Marshall, and Jessica Marshall Spencer. It was dedicated to them February 3, 1974. The fourth donor, Marjorie Congdon Dudley, was honored with The Dudley Experimental Theatre, located inside the center.
Marshall W. Alworth Hall
- General Contractor: Borson Construction
- Mechanical Construction: M. M. Peaslee
- Electrical Installation: Commonwealth Electric
- Casework: St. Charles Kitchens
- Dental Equipment: Kraus Dental Supply
- Fixed Seating: Hawenstein & Burmeister
- Elevator Installation: Johnson Elevator
- Construction Start Date: 7/31/1972
- Architect: Melander, Fugelso and Associates
- Project Cost: $3,596,000
- Completion Date: Summer 1974
Marshall W. Alworth Hall was originally called the Classroom-Laboratory Building and housed the physics department, computer center, dental hygiene clinic and social work graduate school. This building was renamed on March 14 th, 1975 in honor of Marshall W. Alworth Hall who set up the Marshall H. and Nellie Alworth Memorial Fund to award scholarships to medical and natural sciences students.
Residence Hall Dining Center
- General Contractor: A. Hedenberg
- Mechanical Construction: A. G. O'Brien
- Electrical Installation: Lakehead Electric
- Elevator Installation: R & O Electric
- Construction Start Date: 7/26/1971
- Architect: Melander, Fugelso and Associates
- Project Cost: $3,728,425
- Completion Date: July 1974
During the planning of the Residence Hall Dining Center it was referred to as Reception Center and Dining Facility and later, Service Center and Food Service Facility before being called Residence Hall Dining Center.
Ward Wells Field House (Physical Education Field House)
- General Contractor: A. Hedenberg
- Mechanical Construction: Dryke Plumbing & Heating
- Electrical Installation: Electric Construction
- Construction Start Date: 7/31/1973
- Architect: Parker-Klein Associates
- Project Cost: $1,467,301
- Completion Date: 3/10/1975
Ward Wells Field House was named for Ward M. Wells on October 1, 1993. Ward was head of UMD's physical education department for many years.
Sophie DuFresne Concourse
- Contractor: A. Hedenberg
- Construction Start Date: 7/31/1975
- Architect: Partners of Architectural Concern, Inc.
- Project Cost: $371,136
- Completion Date: Summer 1976
Sophie DuFresne Concourse was originally called Residence Hall Concourse during planning, was then named for James and Sophie Du Frensne.
Library Annex
- General Contractor: A. Hedenberg
- Mechanical Construction: Gorham-Oien
- Electrical Installation: Electric Construction
- Construction Start Date: 10/12/1976
- Architect: Thomas and Vecchi, Architects
- Project Cost: $1,343,553
- Completion Date: Fall 1977
The Library Annex was originally the Health Science Library
Research and Field Studies
- General Contractor: A.R. Pavola Construction
- Mechanical Construction: Dryke Plumbing & Heating Co.
- Construction Start Date: October 1977
- Architect:
- Project Cost: $103,913.00
- Completion Date: June 1978
This is information for the Animal Facilities and other buildings.
WDSE TV (Sax Brothers Memorial Communications Center)
- Contractor: Johnson Wilson
- Construction Start Date: April 1977
- Architect: Thomas and Vecchi
- Project Cost: $222,000
- Completion Date: October 1978
(Enter building information here)
Junction Apartments
- Contractor: Lovering, Inc.
- Construction Start Date: April 1978
- Architect: Paul Pink, Inc.
- Project Cost: $1,207,800
- Completion Date: 1/31/1979
Junction Avenue Apartments were originally named Cuyuna Hall and Mesabi Hall to honor two Iron Ranges.
Health Services
- General Contractor: Johnson Wilson Builders
- Construction Start Date: August 1978
- Architect: Melander, Fugelso and Associates
- Project Cost: $380,743
- Completion Date: Summer 1979
Health Services was originally named Chamberlin House.
Glensheen
Original
- Construction Date: 1908
- Architect: Clarence H. Johnston, Sr.
- Civil &Landscape Architect: Charles Wellford Leavitt, Jr.
- Cost: $857,246
Restoration
- Preparation Start Date: March 1979
- Architect: none
- Project Cost: $300,000
- Completion Date: July 1979
Glensheen Mansion was the former home of Chester A. and Clara Congdon. The original family estate sits on 22 acres along the shore of Lake Superior. The home itself is 27,000 sq ft, with 39 rooms, 15 fireplaces, a carriage house, boathouse and pier. Utilities were designed to come into the house underground leaving the landscape and gardens unaffected. The estate became the property of the University of Minnesota Duluth in 1968 and was open for public functions and tours in 1979.
School of Medicine
Phase I
- Contractor: M.A. Mortenson Company
- Heating Tunnel: Nels Nelson & Sons
- Construction Start Date: 7/09/1976
- Project Cost: $354,530
- Heating Tunnel Cost: $143,500
Phase II
- General Construction: A. Hedenberg & Company Inc
- Mechanical Construction: Hayes Inc.
- Electrical Installation: Pemies Electric
- Case Work & Hoods: Charles Kitchen
- Project Cost: $4,834,400
- Completion Date: 9/15/1979
The School of Medicine was originally called UMD Basic Science Building.
Oakland Apartments
- General Contractor: Holms Construction
- Mechanical Construction: Dryke Plumbing and Heating
- Electrical Installation: Lakehead Electric
- Construction Start Date: November 1980
- Architect: Thomas and Vecchi
- Project Cost: $
- Completion Date: Fall 1981
Oakland Avenue Apartments were individually named Oak hall, Aspen Hall, Birch Hall, and Basswood Hall.
School of Business and Economics
Phase I
- General Contractor: A. Hedenberg
- Construction Start Date: October 1979
- Architect: Architectural Resources, Inc.
Phase II
- General Constractor: Hicks Construction
- Mechanical Construction: A. G. O'Brien
- Electrical Installation: Electric Construction
- Architect: Architectural Resources, Inc.
- Project Cost: $3,470,000
- Completion Date: October 1981
(Enter building information here)
Natural Resource Research Institute
Phase I
- General Contractor: Northwest Roofing Contractors
- Construction Start Date: 12/02/1983
- Architect: Stanius/Melander Architects
- Completion Date: 8/01/1984
Phase II
- General Construction: A. Hedenberg and Company, Inc.
- Mechanical Construction: A. W. Kuettel and Sons
- Electrical Installation: Lakehead Electric Company
- Construction Start Date: July 19, 1984
- Architect: Stanius/Melander Architects
- Project Cost: $3,169,063
- Completion Date: January 1986
Formerly the site of the U.S. Air Force base in Duluth.
Engineering
- Contractor:
- General Construction:
- Mechanical Construction:
- Electrical Installation:
- Construction Start Date: 8/19/1985
- Architect: Partners of Architectural Concern, Inc.
- Project Cost: $
- Completion Date: 1986
(Enter building information here)
St. Louis Bay Aquatic Center
- Contractor: Wick Building Systems
- Construction Start Date: November 1988
- Architect: none
- Project Cost: $21,400
- New Space: 2,400 sq ft
- Completion Date:
(Enter building information here)
Solon Campus Center
- General Contractor: Adolphson & Peterson
- Mechanical Construction: A. G. O’Brien Plumbing & Heating
- Electrical Installation: Nylund Electric
- Construction Start Date: April 1994
- Architect: Urban Design Architecture
- Project Cost: $11,500,000
- New Space: 58,000 sq ft
- Completion Date: September 1995
Solon Campus Center was originally called Campus Center before being named after former Senator Sam Solon.
Village Apartments
Phase I
- General Contractor: GME Consultants Inc
- Construction Start Date: March 1994
- Architect: Stanius Johnson
- Project Cost: $4,450,000
- Completion Date: January 1995
Phase II
- Construction Start Date: November 20, 1995
- Architect: Stanius Johnson
- Project Cost: $4,755,000
- New Space: 48,660 sq ft
- Completion Date: 1997
The Village Apartments replaced the Movilla temporary units in 1995.
Chiller Plant
Phase I
- Contractor:Oscar J. Boldt Construction Co.
- Construction Start Date: 5/19/1997
- Architect: Stanius Johnson
- Completion Date: 8/15/1997
Phase II
- Contractor: NewMech
- Construction Start Date: 9/22/1997
- Architect: Stanius Johnson
- Project Cost: $
- Completion Date: 4/01/1998
(Enter building information here)
Library
- Contractor: Oscar J Boldt Construction Co.
Construction Start Date: Summer 1998
- Architect: Stanius Johnson Architects
- Project Cost: $25,800,000
- New Space: 136,000 gross square feet
- Completion Date: September 2000
(Enter info here)
Weber Music Hall
- General Contractor: Johnson Controls
- Mechanical Construction:
- Electrical Installation: Thompson Electric
- Construction Start Date: May 2001
- Architect: Stanius Johnson
- Project Cost: $9,240,000
- New Space: 21,000 sq ft
- Completion Date: August 2002
(Enter building information here)
Chester Park
- Contractor:
Construction Start Date: 2007
- Architect: Architectural Resources, Hibbing, MN
- Project Cost: $5,400,000
- New Space: 56,040 sqft
- Completion Date: Winter 2009
Chester Park School was built in 1927 with upgrades added in 1967. The University purchased the building on June 30, 2006. The building is being used for the College of Education, the Music Department, and the Sea Grant Program.
Coleraine Minerals Research Laboratory
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
(Enter info here)
FENS Research Facility
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
(Enter info here)
Goldfine Hall
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
Goldfine Hall is a complex of three new residence buildings that were dedicated to Erwin L. Goldfine in 1989. Erwin was a regent of the University of Minnesota for twelve years.
Heaney Hall
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
Heaney Hall was named after Judge Gerald Heaney. Judge Heaney was a University of Minnesota regent from 1964 to 1965.
Heaney Hall Service Center
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
(Enter info here)
Limnology
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
(Enter info here)
Northland Advanced Transportation Systems Research Laboratory
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
(Enter info here)
Robert W. Bridges Fleet Grounds Maintenance
- Contractor:
Construction Start Date:
- Architect:
- Project Cost:
- New Space:
- Completion Date:
(Enter info here)
Swenson Science Building
- Contractor: M. A. Mortenson
- Construction Start Date: 4/1/2003
- Architect: Stanius Johnson
- Project Cost: $33,000,000
- New Space: 89,000 sq ft
- Completion Date: 1/31/2005
Swenson Science Building was named for James I. Swenson and Susan Swenson, of the Swenson Family Foundation.
Jim Swenson was a 1959 Chemistry graduate.
Labovitz School of Business and Economics
- Contractor: Oscar Boldt Construction
- Construction Start Date: September 2006
- Architect: Perkins + Will
- Project Cost: $ 23,000,000
- New Space: 65,000 gross sqft
- Completion Date: February 2008
(Enter info here)