Tentative Schedule for 2009 PRC Field Camp
DATE ACTIVITY FACULTY*
5 Sun Check-in to UMD dormitories/Campus tour
.....................Evening introduction & overview .................... .......Peterson, Miller, Hudak (PMH)
Week 1 - Duluth Area (Base-UMD)
6 Mon Introduction to Precambrian field methods Peterson, Goodge
7 Tues Thomson Dam structure mapping project Peterson, Goodge
8 Wed Thomson Dam structure mapping project Peterson, Goodge
9 Thurs Thomson Dam structure mapping project Peterson, Goodge
10 Fri Geophysical field methods ........................ ......... Wattrus
11 Sat Geophysical data analysis ( . . . . . . . .................. Wattrus
12 Sun Free Day .........
Week 2 – Duluth and North Shore Areas (Base-UMD)
13 Mon Spirit Mtn Duluth Complex mapping project Miller
14 Tues Spirit Mtn Duluth Complex mapping project Miller
15 Wed N. Shore Volcanic/Beaver Bay Complex project Miller
16 Thurs N. Shore Volcanic/Beaver Bay Complex project Miller
17 Fri N. Shore Volcanic/Beaver Bay Complex project Miller
18 Sat Free Day
19 Sun Move camp to Vermilion Community College
Week 3 – Ely and Mesabi Range Areas (Base-VCC)
22 Mon Mesabi Range project - core logging Severson, Jirsa
21 Tues Mesabi Range project - pit mapping Severson, Jirsa
22 Wed Mesabi Range project - core logging Severson, Jirsa
23 Thurs Basal Duluth Complex project - mapping Peterson
24 Fri Basal Duluth Complex project - core logging Peterson
25 Sat Greenstone field trip/Soudan Mine mapping Peterson, Hudak
26 Sun Free Day
Week 4 - Ely Area (Base-VCC)
27 Mon Granite-greenstone bedrock and glacial mapping Hudak, Mooers, Peterson
28 Tues Granite-greenstone bedrock and glacial mapping Hudak, Mooers, Peterson
29 Wed Granite-greenstone bedrock and glacial mapping Hudak, Mooers, Peterson
30 Thurs Granite-greenstone bedrock and glacial mapping Hudak, Mooers, Peterson
31 Fri Granite-greenstone bedrock and glacial mapping Hudak, Mooers, Peterson
1 Sat Free day
2 Sun Move out of VCC; Head to capstone project areas
Week 5 (Sun, 2nd – Sat, 8th)– Capstone Mapping Project
1. Homer Lake area (eastern Duluth Complex) Miller
2. Disappointment Mtn area (Duluth Complex-Archean contact) Peterson
3. Disappointment Mtn area (Duluth Complex-Archean contact) Hudak
4. Ham Lake Fire area (Archean/Paleoproterozoic terranes) Jirsa
5. Grand Marais area (North Shore Volcanics) Boerboom
9
Sun Move back to UMD dormitories
Week 6 - University of Minnesota Duluth GIS Lab
10 Mon Introdution to ArcView and Illustrator ................... PMH
11 Tues Compilation of field data, map interpretation PMH
12 Wed Compilation of field data, map interpretation PMH
13 Thurs Compilation of field data, map interpretation PMH
14 Fri "Graduation" - Final Map presentations PMH, Guests
15 Sat Move out of UMD dorms; End of Camp
* Individuals indicated will have primary responsibility for overseeing that day’s activity. Full-time PRC staff (PMH) will also assist each day. Visiting faculty are welcome any time.
|